M-36 ROAD CONSTRUCTION - RESURFACING, July 6 through mid-September

Contact:  Kari Arend, MDOT Office of Communications,
arendk@michigan.gov 
517-206-1609

Agency: Transportation
 

COUNTIES: Ingham and Livingston

HIGHWAY: M-36

CLOSEST CITY: Gregory

START DATE: Tuesday, July 6, 2010

END DATE: Mid-September 2010

PROJECT: The Michigan Department of Transportation (MDOT) will oversee a project this year to resurface 7.5 miles of M-36 between M-106 and M-52.

All work is expected to be complete by mid-September.

TRAFFIC RESTRICTIONS: During construction, one lane will be maintained during daylight hours with flag control. Where work is taking place, the maximum length of the closure will be 2 miles long.

Access to all intersecting streets and driveways will be maintained at all times.

MDOT says: Construction work zones need your undivided attention